Home >> Key Project >> National Cyclone Risk Mitigation Project(NCRMP ) >> UNDERGROUND CABLING WORK (PACKAGE-2) UNDER NCRMP-II PHYSICAL PROGRESS

UNDERGROUND CABLING WORK (PACKAGE-2) UNDER NCRMP-II PHYSICAL PROGRESS

Sl. No. Description Target Completed
1 HT Cable Laying 70.613 Km 70.613 Km
2 LT Cable Laying 140.315 Km 140.315 Km
3 FO Cable Laying 49.577 Km 49.577 Km
4 Service Cable Laying 212.517 Km 212.517 Km
5 1 Phase Meter Cable Laying 4785 Nos. 4785 Nos.
6 3 Phase Meter Cable Laying 744 Nos. 744 Nos.
7 1 Phase Meter Connection 4785 Nos. 4785 Nos.
8 3 Phase Meter Connection 744 Nos. 744 Nos.