Home >> Key Project >> National Cyclone Risk Mitigation Project(NCRMP ) >> UNDERGROUND CABLING WORK (PACKAGE-2) UNDER NCRMP-II PHYSICAL PROGRESS

UNDERGROUND CABLING WORK (PACKAGE-2) UNDER NCRMP-II PHYSICAL PROGRESS

Sl. No. Description Target Completed
1 HT Cable Laying 70.675 Km 70.316 Km
2 LT Cable Laying 140.274 Km 139.608 Km
3 FO Cable Laying 50 Km 50 Km
4 Service Cable Laying 212.536 Km 212.536 Km
5 1 Phase Meter Cable Laying 4,610 Nos. 4,610 Nos.
6 3 Phase Meter Cable Laying 714 Nos. 714 Nos.
7 1 Phase Meter Connection 4,610 Nos. 4610 Nos.
8 3 Phase Meter Connection 714 Nos. 714 Nos.